SSC CGL 2023 PYQ — Question 65

SSC CGL - 17 July 2023 - Shift 3 • Quantitative Aptitude • Q65

12 men and 16 boys can do a piece of work in 5 days, while 13 men and 24 boys can do it in 4 days. In how many days can 29 men and 22 boys complete the work?

Show answer & explanation

Correct answer: A

Explanation

The correct answer is Option 1 i.e. 2.5.

Calculations:

Let the efficiency of a man and a boy be M and B

According to the question;

⇒ (12M + 16B) × 5 = (13M + 24B) × 4

⇒ 60M + 80B = 52M + 96B

⇒ 8M = 16B

⇒ M/B = 2/1

Total work = (12M + 16B) × 5 = 200

Required time taken = 200/(29M + 22B)

⇒ 200/(58 + 22) = 200/80

⇒ 2.5 days