10 men can complete a piece of work in 8 days. How many men are required to complete the same work in 5 days?
Show answer & explanation
Correct answer: C
Explanation
Given:
10 men complete the work = 8 days
Work to be completed = 5 days
Formula:
Men × Days = Constant
10 × 8 = M × 5
80 = 5M
M = 16
16 men