SSC CHSL 2025 PYQ — Question 27

SSC CHSL - 17 Nov 2025 - Shift 1 • Reasoning • Q27

10 men can complete a piece of work in 8 days. How many men are required to complete the same work in 5 days?

Show answer & explanation

Correct answer: C

Explanation

Given:

10 men complete the work = 8 days

Work to be completed = 5 days

Formula:

Men × Days = Constant

10 × 8 = M × 5

80 = 5M

M = 16

16 men